Expac is moving – Page 09
Blog update 7 – lucky – 7 – !!
Yes the clock is right less than four weeks to go and the sleepless nights continue
Look closely at the photographs and compare them with the ones taken several weeks ago – The project has moved on a lot and we are now starting to see our vision come reality
Contractors are starting to complete their various individual projects and whole fit out is coming together – better than we envisaged – we might add
This is what we have achieved in the last seven days – We say seven as the site has had contractors working every day of the week for the past few works to adhere to our time plan
This slideshow requires JavaScript.
- All heaters now installed waiting gas connection
- All heat blowers installed
- Electrical fit our continues
- Trench and main new cable waiting for connection
- New sun station getting fitted Sunday 27th November – hope to get you a picture of this
- Internal production rooms all finished and sealed and vacuum tested
- New Aco 10 metre drain fitted for internal wash down
- More stock moved in to holding unit 1
- Laboratory constructed
- Office fit our continues ready for hand over by HB on Wednesday 30th November
- New staircase and painting / floor covering being installed in offices
- Full wash down off the floors and walls commenced
So as the main contractors start to back out we will be handed over to our factory move and installation team
We should be in a position on the next blog to update on exact move dates for various lines etc
Please keep following our progress
The pictures don’t give the effort just rewards however I am sure you will all visit in the not too distant future
Thank you again