Expac is moving – Page 06

Blog Update 4  – 29th October 2010

7 weeks in and half way in the project

The following has been achieved in the last 7 days

  • Some internal walls have been painted white using food grade paint and three coats
  • The production area floor space – 20,000 square feet has been shot blasted ready for industrial coating
  • Internal steel supports have been painted – grey
  • The electrical fit out continues all the new lighting is complete
  • The deep clean of the full site has been completed
  • We have commenced cladding some of the internal walls to be covered at a later time with wipe down food grade PVC impact resistant lining
  • Office construction continues / HP are on target for their strict time scale
  • First fix electrics in the office complex has been completed
  • First fix on the new fire alarm to the site has been completed
  • Plastering team have started work on site
  • Various floor levels have been adjusted / broken out and re laid
  • Suspended ceiling team have commenced the new ceiling fit out in the offices
  • The plumbing contractor has commenced the new plumbing work to be carried out
  • Drainage work has commenced / all new drainage to offices and mixing plant

Well as you can see plenty going on / on a daily basis there have been over fifty contactors on site daily

This slideshow requires JavaScript.

As previously mentioned this is not just a “paint over” project – The reason we are being totally transparent about the move and the project is we want to create a facility we can be proud off but also a point of difference – create a standard that makes Expac stand out from the crowd.

We have even made sure all the waste and debris we have taken from the building has been disposed of correctly / please find an example of the recycling report we get produced every week as you can see 99% of the rubbish has been recycled.

So in summary we are looking cleaner – It’s now a case of putting everything back to the highest standard – It is also pleasing to know we are still on budget and within in our time scale –

Till the next time – Thank you for following our journey – You don’t have to wait till we are finished to visit – If would like to look around at any time please do not hesitate to contact our business development team

Thank you -

PS – Sorry if the grammar or spelling is not as a top class editor would write however these weekly. / Fortnightly updates are written as they happen / a daily dairy xx

Canteen wall installed and Mezzanine floor in place

New lighting through out the building installed.

Exterior landscaping work started.

First stage of office build underway.

Staff entrance under construction.

Staff canteen interior walls.

Rear view of new office block under construction.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s


Follow

Get every new post delivered to your Inbox.

%d bloggers like this: