Expac is moving – Page 06
Blog Update 4 – 29th October 2010
7 weeks in and half way in the project
The following has been achieved in the last 7 days
- Some internal walls have been painted white using food grade paint and three coats
- The production area floor space – 20,000 square feet has been shot blasted ready for industrial coating
- Internal steel supports have been painted – grey
- The electrical fit out continues all the new lighting is complete
- The deep clean of the full site has been completed
- We have commenced cladding some of the internal walls to be covered at a later time with wipe down food grade PVC impact resistant lining
- Office construction continues / HP are on target for their strict time scale
- First fix electrics in the office complex has been completed
- First fix on the new fire alarm to the site has been completed
- Plastering team have started work on site
- Various floor levels have been adjusted / broken out and re laid
- Suspended ceiling team have commenced the new ceiling fit out in the offices
- The plumbing contractor has commenced the new plumbing work to be carried out
- Drainage work has commenced / all new drainage to offices and mixing plant
Well as you can see plenty going on / on a daily basis there have been over fifty contactors on site daily
As previously mentioned this is not just a “paint over” project – The reason we are being totally transparent about the move and the project is we want to create a facility we can be proud off but also a point of difference – create a standard that makes Expac stand out from the crowd.
We have even made sure all the waste and debris we have taken from the building has been disposed of correctly / please find an example of the recycling report we get produced every week as you can see 99% of the rubbish has been recycled.
So in summary we are looking cleaner – It’s now a case of putting everything back to the highest standard – It is also pleasing to know we are still on budget and within in our time scale –
Till the next time – Thank you for following our journey – You don’t have to wait till we are finished to visit – If would like to look around at any time please do not hesitate to contact our business development team
Thank you -
PS – Sorry if the grammar or spelling is not as a top class editor would write however these weekly. / Fortnightly updates are written as they happen / a daily dairy xx
Canteen wall installed and Mezzanine floor in place
New lighting through out the building installed.
Exterior landscaping work started.
First stage of office build underway.
Staff entrance under construction.